Building with Sakaan

RAPIDWALL is a cost-competitive lightweight building material erected more easily and speedily than conventional building materials.

After completion of the foundation or the concrete suspended floor onto which RAPIDWALL is to be positioned, the builder’s surveyors establish and mark all main grid lines.

  • Using the architectural layout drawings, a trained RAPIDWALL Erection Crew marks out the walling positions in reference to these grid lines
  • For the first floor, the concrete foundation is drilled and starter bars are epoxied into place. For subsequent floors, starter bars extend from the panel below
  • Weighing up to 5 tonnes, the laden stillage containing the cut RAPIDWALL panels selected for erection is then lifted by crane onto the concrete floor or foundation prepared to receive the panels
  • One by one, the cut RAPIDWALL panels are decanted from the stillage by crane and placed into their final position, propped, and then connected in accordance with the installation guidelines
  • To construct the next suspended floor spanning between the load-bearing RAPIDWALL , formwork is installed and propped. After this, it is used as staging to pump concrete into the cells of the RAPIDWALL
  • Whilst still plastic, starter bars are placed in the concreted cells in readiness for the next floor of RAPIDWALL panels
  • Slab reinforcement is placed on the formwork and the concrete poured for the next suspended floor

APPLICATIONS

Materials usedRapidwall BuildingConventional BuildingSaving in %
Cement 16 tonnes 32.55 tonnes 50.8
Steel 1800 kg 2779 kg 35.2
River sand 20 m3 83.37 m3 76
Granite metal 38 m3 52.46 m3 27.56
Bricks - 57200 -
Rapidwall 500m²
Water 50000lt 200000lt 75
Built Area 143m² 143m² 8
Labour 389 man days 1200 man days 67.59
Construction Time 21 days 120 days 82
Total Weight of superstructure 170 tonnes 490 tonnes 65
Construction Cost $US 26,800 $US 36,980 27.5
Embodied energy in kWh 82921 61.5 61.5
Share This